Data centers are getting their own natural gas power plants

Sentiment: Neutral ⚖️
By Funded4Trading  ·  November 24, 2026  ·  1 min read  ·  1 views
Advertisement

One of the biggest roadblocks to starting up a data center is getting approval to connect to the electric grid—a wait that could last as long as a decade.

Some developers aren’t willing to wait and are instead opting to build their own off-grid, or behind-the-meter, gas power plants to fuel the AI boom.   xAI’s Memphis campus has famously used dozens of natural gas turbines, some of them without permits, as far back as 2024.

At the time, that facility was a rarity, and it faced scrutiny from regulators.

It remains the subject of ongoing legal battles.

But the strategy of going off-grid for power has since become a lot more common.

As of October 2026, data center developers have announced plans for more than 100 behind-the-meter gas power plants at facilities in the US, according to data from Cleanview, a market intelligence company.

The facilities have a combined planned capacity of over 115 gigawatts, more than double the peak power demand of California.

The vast majority of these announcements have come since the beginning of 2025.

It’s possible that not all these facilities will be built; only a small fraction are under construction or operating today.